{"id":6616,"date":"2021-10-12T10:10:00","date_gmt":"2021-10-12T08:10:00","guid":{"rendered":"https:\/\/commercecon.pl\/baza-wiedzy\/odbior-hali-produkcyjnej\/"},"modified":"2022-05-23T12:30:50","modified_gmt":"2022-05-23T10:30:50","slug":"production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction","status":"publish","type":"knowledge","link":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/","title":{"rendered":"Production hall commissioning \u2013 necessary documents at the final stage of hall construction"},"content":{"rendered":"\n<div class=\"wp-block-group is-style-container\"><div class=\"wp-block-group__inner-container is-layout-flow wp-block-group-is-layout-flow\">\n<div class=\"wp-block-cover\"><img loading=\"lazy\" decoding=\"async\" width=\"1920\" height=\"1279\" class=\"wp-block-cover__image-background wp-image-4530\" alt=\"\" src=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg\" style=\"object-position:56% 70%\" data-object-fit=\"cover\" data-object-position=\"56% 70%\" srcset=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg 1920w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3-300x200.jpg 300w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3-1024x682.jpg 1024w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3-768x512.jpg 768w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3-1536x1023.jpg 1536w\" sizes=\"auto, (max-width: 1920px) 100vw, 1920px\" \/><div class=\"wp-block-cover__inner-container is-layout-flow wp-block-cover-is-layout-flow\">\n<p class=\"has-text-align-center has-large-font-size\"><\/p>\n<\/div><\/div>\n\n\n\n<style>\n    @media (max-width:1023px) {\n        .spacer-block_60d9c7687c63e {\n            height: 10px;\n        }\n    }\n    @media (min-width:1024px) {\n        .spacer-block_60d9c7687c63e {\n            height: 50px;\n        }\n    }\n<\/style>\n<div class=\"spacer spacer-block_60d9c7687c63e\"><\/div>\n\n\n\n<div class=\"wp-block-group is-style-container-small\"><div class=\"wp-block-group__inner-container is-layout-flow wp-block-group-is-layout-flow\">\n<p><strong>What does the construction of a production hall end with? It is putting the facility into service. However, in order for this to be possible, all documents essential for the facility commissioning must be collected. What documents are being referred to? When should they be gathered?\u00a0 What are the basic stages of a steel hall commissioning?<\/strong><\/p>\n\n\n\n<p><strong>Commissioning of a building \u2013 documents required<\/strong><\/p>\n\n\n\n<p>The commissioning of a production hall will not be possible without the so-called as-built documentation. What documents are necessary for the commissioning of a building? Whether it is a production hall, <a href=\"https:\/\/commercecon.pl\/en\/industrial-facilities\/sports-and-event-halls\/\">a sports hall<\/a>, a storage facility or a cold storage or refrigeration facility, various reports and permits must be collected. The most important include: the construction permit design, taking into account any changes made during the construction work, a statement of the construction manager, the construction logbook \u2013 the original, as-built survey documentation, all reports from technical tests of the systems, technical equipment installed, flues and stacks, also technical supervision permits for the operation of the technical equipment where appropriate (for example lifting equipment), confirmation of acceptance of utility connections and the quality of construction materials used. Some documents are returned when the technical acceptance of the building is completed, others remain with the office.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"683\" height=\"1024\" src=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/3-1-683x1024.jpg\" alt=\"odbi\u00f3r hali produkcyjnej - instalacja\" class=\"wp-image-4534\" srcset=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/3-1-683x1024.jpg 683w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/3-1-200x300.jpg 200w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/3-1-768x1151.jpg 768w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/3-1.jpg 800w\" sizes=\"auto, (max-width: 683px) 100vw, 683px\" \/><\/figure>\n\n\n\n<p><strong>Permits \u2013 who should apply, when and to whom?<\/strong><\/p>\n\n\n\n<p>What authorities should be notified once the above documents have been collected? If the investor is obliged to obtain an occupancy permit for the hall, or if the building project was subject to agreements with regard to fire protection and hygiene and health conditions, the first points of contact are the District Sanitary and Epidemiological Station (PSSE) and the District Headquarters of the State Fire Service (PSP). Note that <a href=\"https:\/\/commercecon.pl\/en\/\">industrial construction<\/a> often requires the above-mentioned services to take a position on the matter in question. This is the case, among others, for the production and commercial and exhibition halls, including those intended to serve as shopping centres.<\/p>\n\n\n\n<p><strong>Acceptance of a production hall by the construction supervision authority<\/strong><\/p>\n\n\n\n<p>A facility built without a building permit, i.e. not required to report to the sanitary and epidemiological station and fire service headquarters, should be approved by the construction supervision authority based on a notice of completion of construction works. In case of industrial halls where a building permit is required, an application is made for an occupancy permit and the positions of the PSP and PSSE are also necessary.<\/p>\n\n\n\n<p>The application for an occupancy permit becomes a call for inspection. The inspection is carried out within 21 days of the date of the application receipt and the investor is notified of the exact date of the inspection within 7 days. Importantly, the investor must participate. Once this has been completed, an acceptance report is drawn up and, if all goes well, an occupancy permit is issued by decision.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"682\" src=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2-1024x682.jpg\" alt=\"odbi\u00f3r hali produkcyjnej - ty\u0142 hali\" class=\"wp-image-4532\" srcset=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2-1024x682.jpg 1024w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2-300x200.jpg 300w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2-768x512.jpg 768w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2-1536x1023.jpg 1536w, https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/2-2.jpg 1920w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<p>What is verified during the inspection? Mainly the conformity of the building completion with the construction project, the quality of the materials used, as well as the current condition of the site \u2013 everything should be cleaned and tidied up before the application is submitted.<\/p>\n\n\n\n<p>The first case concerns other matters and consists in notifying the construction supervision authority of the completion of the construction work. The supervisory authority has 14 days from the submission of the notice to object by decision. If it fails to do so, it is considered that the facility may be put into operation. The same happens if the supervisory authority issues a certificate of occupancy earlier, i.e. within 14 days.<\/p>\n<\/div><\/div>\n<\/div><\/div>\n","protected":false},"featured_media":4531,"template":"","realizacje-obiekt":[328,312,175,173],"class_list":["post-6616","knowledge","type-knowledge","status-publish","has-post-thumbnail","hentry","realizacje-obiekt-budowa-hali-en","realizacje-obiekt-industrial-facility","realizacje-obiekt-production-and-storage-halls","realizacje-obiekt-production-halls"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v26.4 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon\" \/>\n<meta property=\"og:description\" content=\"What does the construction of a production hall end with? It is putting the facility into service. However, in order for this to be possible, all documents essential for the facility commissioning must be collected. What documents are being referred to? When should they be gathered?\u00a0 What are the basic stages of a steel hall [&hellip;]\" \/>\n<meta property=\"og:url\" content=\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/\" \/>\n<meta property=\"og:site_name\" content=\"Commercecon\" \/>\n<meta property=\"article:modified_time\" content=\"2022-05-23T10:30:50+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1920\" \/>\n\t<meta property=\"og:image:height\" content=\"1279\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data1\" content=\"4 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/\",\"url\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/\",\"name\":\"Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon\",\"isPartOf\":{\"@id\":\"https:\/\/commercecon.pl\/en\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg\",\"datePublished\":\"2021-10-12T08:10:00+00:00\",\"dateModified\":\"2022-05-23T10:30:50+00:00\",\"breadcrumb\":{\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage\",\"url\":\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg\",\"contentUrl\":\"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg\",\"width\":1920,\"height\":1279,\"caption\":\"fot. www.jacekolszewski.com\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Main\",\"item\":\"https:\/\/commercecon.pl\/en\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Investor's guide\",\"item\":\"https:\/\/commercecon.pl\/en\/baza-wiedzy\/\"},{\"@type\":\"ListItem\",\"position\":3,\"name\":\"Production hall commissioning \u2013 necessary documents at the final stage of hall construction\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/commercecon.pl\/en\/#website\",\"url\":\"https:\/\/commercecon.pl\/en\/\",\"name\":\"Commercecon\",\"description\":\"\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/commercecon.pl\/en\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/","og_locale":"en_US","og_type":"article","og_title":"Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon","og_description":"What does the construction of a production hall end with? It is putting the facility into service. However, in order for this to be possible, all documents essential for the facility commissioning must be collected. What documents are being referred to? When should they be gathered?\u00a0 What are the basic stages of a steel hall [&hellip;]","og_url":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/","og_site_name":"Commercecon","article_modified_time":"2022-05-23T10:30:50+00:00","og_image":[{"width":1920,"height":1279,"url":"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg","type":"image\/jpeg"}],"twitter_card":"summary_large_image","twitter_misc":{"Est. reading time":"4 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/","url":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/","name":"Production hall commissioning \u2013 necessary documents at the final stage of hall construction - Commercecon","isPartOf":{"@id":"https:\/\/commercecon.pl\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage"},"image":{"@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage"},"thumbnailUrl":"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg","datePublished":"2021-10-12T08:10:00+00:00","dateModified":"2022-05-23T10:30:50+00:00","breadcrumb":{"@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#primaryimage","url":"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg","contentUrl":"https:\/\/commercecon.pl\/wp-content\/uploads\/2021\/10\/1-3.jpg","width":1920,"height":1279,"caption":"fot. www.jacekolszewski.com"},{"@type":"BreadcrumbList","@id":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/production-hall-commissioning-necessary-documents-at-the-final-stage-of-hall-construction\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Main","item":"https:\/\/commercecon.pl\/en\/"},{"@type":"ListItem","position":2,"name":"Investor's guide","item":"https:\/\/commercecon.pl\/en\/baza-wiedzy\/"},{"@type":"ListItem","position":3,"name":"Production hall commissioning \u2013 necessary documents at the final stage of hall construction"}]},{"@type":"WebSite","@id":"https:\/\/commercecon.pl\/en\/#website","url":"https:\/\/commercecon.pl\/en\/","name":"Commercecon","description":"","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/commercecon.pl\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"}]}},"_links":{"self":[{"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/knowledge\/6616","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/knowledge"}],"about":[{"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/types\/knowledge"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/media\/4531"}],"wp:attachment":[{"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/media?parent=6616"}],"wp:term":[{"taxonomy":"realizacje-obiekt","embeddable":true,"href":"https:\/\/commercecon.pl\/en\/wp-json\/wp\/v2\/realizacje-obiekt?post=6616"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}